Recent contracts |
|
|
|
Aztec International Ltd completed 2 Exploration wells in Miri East, during October and November 2011 for Baker Hughes, on behalf of Nippon Oil (NOEX), with Aztec Rig #14.
Both of these wells were on the East divide of the Miri fault line, in Borneo, and were completed successfully in a short time, with no lost time accidents.
Following that contract, in Jan 2012, Aztec Rig #7 set off to the Northern tip of the Phillipines to drill out the base of an existing gas well which had been plugged and abandoned, at 3014 metres,
Tubing was then run, and the well was tested. Once again, no incidents and a successful completion.
Aztec was then called on by Mitra Energy to drill a very sensitive, exploration well in the heart of Bangkok, in March 2012. The environmentalists were out in force, and the rig height was limited to 31m, from the ground to the top of the derrick. The well site was situated amongst multi million dollar elite homes, in the heart of Bangkok, and noise restrictions and spills were of great concern.
In spite of only being able to drill, and rack single joints, this project was completed within 30 days, to a depth of 2499 metres, with no accident, another highly successful operation.
The current projects, as of June 2012, involve 7 wells at The Phimai Salt Company in Thailand, and approx 20 work-overs for the same company.
We look forward to working with all of the major Oil Companies in the near future.
|
|
|
|
|
|
|
|